Progress report

Oct 2006

Praise God! After acquiring 35 acres of property just under 1 year ago God is moving very fast. We started by putting in a road and cutting a pad. We then put up a temporary shed, put in a septic system and started the footings for the warehouse. In December 2005, we received a tractor. We built an area to lock up the tractor and had a team from Tennessee come down to put a roof on the tractor shed and started building the first restrooms.

In July 2006 we met with a contractor about costs for the first 2 houses. After much prayer we contacted our friends in Tennessee to let them know what was going on. A  short period of time they said we should go ahead and have the first 2 houses done as soon as possible. This brings us up to August 18th the first meeting with the contractor, and engineer. They broke ground August 21 and have not stopped yet. Today is October 25th and the houses are ready for the roof and the warehouse is done, and we have electricity.

 

                                        

 

                                        

 

The footings for the kitchen and laundry room, which are the only enclosed rooms in the multi-purpose room / church are done and we know await a team from our church to put up the walls.